Outline of Process

Outline of Process

Outline of Process  

This period can be from one month to several months depending on each town, land, home design, engineering etc…. 

1. Exploratory
(a) Review our Portfolio for inspiration or bring your plans for us to modify.
(b) Begin financial discussions with a lender, and purchase land
(c) Set a budget to include - land , site work, site engineering with drainage allowances
(d) Meet with a CMH Custom Homes Sales Associate
(e) Receive a CMH Custom Homes Package Quote
(f)Timeline: varies by client
(g) During this period a surveyor & engineering team should also be readied to hire if not us.
2. Schematic Design
(a) Choose an existing plan and move directly to Deposit, or...
(b) Place a Design Retainer and work with a CMH Design Team Project Manager on plan & development
(c) Receive a Schematic Design Package and Quote
(d) Timeline: One Month.
3. Design Development
(a) Make final modifications to the design
(b)Complete construction and foundation plans
(c)Secure financing Sign CMH Contract
(d) Place deposit on CMH Home package
(e) Submit the permitting application
(f) Timeline: 1-2 Months

4. Building Start

(a) once permit are issued we immediatley release deposit funds to beginning the modular build in the factory. Ordering windows, doors, etc....
(b) At The Site: Excavation, installation of utilities and foundation, and management of other necessary site preparation is completed.
(c) Timeline: 1-2 Months

5. Construction

(a)Modulars are delivered and stored onsite or near the site.

(b)The erraction or set of the home starts and is made weather tight. 


(c) Timeline: 5-7 days

 

6. Completion - Onsite Work

(a) Back fill of Foundation

(b) Siding, Masonry, Electrical, HVAC, Plumbing , Millwork, drywall, all happen on site now

(c) Flooring and painting and landscaping


(d) Timeline: 45-120 days